Hania Ali is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the project activities, she and the project team have agreed to crash the project work. What must be true of these project activities for crashing to be acceptable?
- The activities must be of fixed duration.
- The activities must be effort-driven.
- The activities must not be susceptible to the Law of Diminishing Returns.
- The activities must be risk-free.
The purpose of posting these questions is to enhance knowledge and encourage diverse perspectives. By participating, you have the opportunity to share your own insights in the comments section, while also benefiting from the viewpoints of others. This exchange of ideas can contribute significantly to your understanding of the subject. We encourage you to engage actively, express your thoughts clearly, and provide well-considered answers. After a few days (typically within two to seven), we will share the correct answer along with a comprehensive explanation.
👉🏻WEB: https://planningp6.com/
👉🏻YOUTUBE: https://www.youtube.com/@PLANNINGP6/f...
👉🏻LINKEDIN: https://www.linkedin.com/in/planning-p6/
👉🏻FACEBOOK: https://www.facebook.com/profile.php?...
👉🏻SHOP: https://planningp6.com/p6-shop/
👉🏻DISCUSSION FORUM: https://planningp6.com/discussions/
👉🏻WHATSAPP: https://wa.me/923088663797?text=Hello....
▶ PRIMAVERA P6 SOFTWARE (ALL VERSIONS): https://www.youtube.com/playlist?list=PLIiIVGUn-oNpDNGhEA_9IrBxD5FCNjQz3
▶ P6 SOFTWARE & SCHEDULING: https://www.youtube.com/playlist?list=PLIiIVGUn-oNqfYWzEyIZIU8t-qQJe5QFQ
▶ COMPLETE PROJECTS: https://www.youtube.com/playlist?list=PLIiIVGUn-oNqDpHKJaod1Hn-yiEAkO7Fk
▶COST AND CLAIM MANAGEMENT: https://www.youtube.com/playlist?list=PLIiIVGUn-oNpUcYGFwila2dlL1Ornwgev
▶MONITORING PHASE: https://www.youtube.com/playlist?list=PLIiIVGUn-oNo2GZb44PtTKX4jZEaM9hX4 Â
▶CONTROLLING PHASE: https://www.youtube.com/playlist?list=PLIiIVGUn-oNrkyLw6WZzt_CZsEBLXT8sP