Ledger of Delays

This standardized format facilitates the recording and communication of project delays to stakeholders. The document includes columns with advanced filtering capabilities for efficient analysis.

  1. Serial Number
  2. Activity ID (As Schedule)
  3. Description / Activity Name
  4. Date       (From-To)
  5. Time      (From-To)
  6. Personnel Engaged for The Activity
  7. Manhours Lost
  8. Hours Lost
  9. Days Lost
  10. Critical /Non-Critical
  11. Delay Type
  12. Reason of Delay
  13. Report Reference Details (Document Number)
  14. Remarks