Description:
In project management, especially when working with Primavera P6, the concept of a baseline is crucial. Baselines act as a reference point to measure how the project is performing compared to the original approved plan. However, many planners, schedulers, and project managers often get confused when it comes to the terms Primary Baseline and Project Baseline.
While both serve the purpose of comparison, they are not the same. Understanding the distinction is essential for accurate project monitoring, reporting, and communication with stakeholders.
In this article, we’ll explore the difference between Primary Baseline and Project Baseline, their specific roles, and why using them correctly is critical for effective project control.
What is a Baseline in Primavera P6?
Before diving into the differences, let’s first clarify what a baseline means in general.
A baseline in Primavera P6 is a snapshot or a copy of your project schedule at a given point in time. It preserves all activities, dates, durations, resources, and costs. By comparing the current schedule with the baseline, planners can easily identify delays, deviations, or improvements.
Think of it as freezing your plan on a certain date, so that you can always go back and measure your progress against that frozen plan.
t’s a useful tool. But the challenge comes when we apply these rigid rules to construction scheduling, where reality doesn’t always match the math.
What is a Primary Baseline?
Key Characteristics of a Primary Baseline:
- It is the main baseline used for performance measurement.
- It shows up in the tracking layout with baseline bars under the current schedule bars.
- Variance fields (such as Start Variance, Finish Variance, and Duration Variance) are calculated based on the Primary Baseline.
- Only one Primary Baseline can be assigned at a time, but you can switch between different baselines depending on reporting needs.
What is a Project Baseline?
- It is used primarily for earned value calculations (such as Planned Value, Earned Value, and Cost Performance Index).
- It acts as the overall benchmark of the project.
- It helps management see whether the project is performing against the original approved baseline.
- Like the Primary Baseline, you can select any baseline to act as the Project Baseline, but usually it is set only once at the beginning.
Primary Baseline vs. Project Baseline – The Core Difference
Aspect
Primary Baseline
Project Baseline
Purpose
Used for day-to-day schedule variance tracking
Used for overall project performance and earned value
Scope
Activity-level comparison (start/finish dates, durations, floats)
Project-level comparison (cost, budget, earned value)
Default Role in P6
Shows baseline bars and calculates variance fields
Used in Earned Value Management calculations
Flexibility
Can be reassigned frequently for different reporting needs
Usually set once and rarely changed
In simple words:
- Primary Baseline = Day-to-day reference for tracking schedule progress.
- Project Baseline = Original approved plan for high-level reporting and earned value.
Why is This Difference Important?
Maintain Consistency – Project Baseline should remain stable for accurate high-level reporting, while the Primary Baseline can be flexible.
Best Practices for Using Baselines in Primavera P6
Set the Primary Baseline based on current needs – For example, you may set your most recent updated baseline as the Primary Baseline for detailed tracking.
Communicate clearly with stakeholders – Ensure management knows which baseline you are reporting against.
Keep multiple baselines if needed – Primavera P6 allows you to maintain several baselines, so you can compare performance across different versions.
CONCLUSION
In Primavera P6, both Primary Baseline and Project Baseline play critical roles, but they serve different purposes. The Primary Baseline helps you track schedule variances at the activity level, while the Project Baseline provides a fixed benchmark for overall project performance and earned value analysis.
For planners and schedulers, mastering this difference ensures accurate reporting and better project control. For managers, it means clearer insight into whether the project is on track compared to the original plan.
By using both baselines correctly, you can provide transparent, reliable, and professional project updates, exactly what successful project management requires.
ADDITIONAL RESOURCES
For a comprehensive understanding, we recommend exploring our dedicated tutorials on Primavera P6 relationships. These tutorials are accessible through our Planning P6 Tutorials Dictionary (REV-003). Simply search for keywords like “relationship” or “Primavera P6 integration” to access relevant content.
PLANNING P6 TUTORIALS
How to do Advanced Reporting, Effective Analysis & Comparison in Primavera P6 for Multiple Projects
How to Review Primavera P6 Schedule | Schedule Review Checklist | Best Practices for Schedule Review
How Much Total Float Is Allowed in Project Primavera P6 | How to Reduce Total Float in Project #P6
How to Identify and Analyze Float Paths in primavera P6 | Filter, Group and Sort Float Paths in P6 |

What are schedule levels in Primavera P6 | Understanding Schedule levels & How to Customize in #P6 |